Appendix 1
Highways Service Performance Indicators - Year 1
Reporting Period |
Year 1 Result |
|
Performance Area |
SPI Description |
YTD Performance |
Quality Assurance |
SPI 01 – Defects response within time |
98.8% |
SPI 02 – Safety defect correction within time for Carriageway/Cycleway/Footway asset types |
71.7% |
|
SPI 03 – Safety defects correction within time for other asset types |
86.2% |
|
SPI 04 – Safety defects permanently repaired first time |
91.3% |
|
SPI 05 – Winter Maintenance – Precautionary Treatments |
100.0% |
|
SPI 06 – Defect free works |
65.6% |
|
SPI 07 – Notified Defects |
100.0% |
|
SPI 08 – Programme Delivery – Work Activities |
76.8% |
|
SPI 09 – Final Accounts |
90.5% |
|
SPI 10 – Permit regulations met on site |
78.4% |
|
Stakeholder Engagement |
SPI 11 – Well planned permits |
90.5% |
SPI 12 – Work Activities started on time |
81.8% |
|
SPI 13 – Works communications |
92.8% |
|
SPI 14 – Communications - Timely Response |
93.6% |
|
SPI 15 – Third-party claims timely response |
|
|
Promote Economic Growth |
SPI 16 – Social Value Plan Commitments |
99.8% |
SPI 17 – Local Spend |
61.1% |
|
Nil Return |
|
|
SPI is Above or Equal to Target |
|
|
SPI is within 10% of Target |
|
|
SPI is below 10% of Target |
|
Performance Level Target - Year 1 |
91.9% |
Performance Level Achieved - Year 1 |
86.2% |
Normalised Performance Level - Year 1 |
93.8% |
Highways Key Performance Indicators
Outcomes |
KPI No. |
Name |
Brief description |
Quality Assurance |
1 |
KPI 1 |
Combined SPI 1-10 performance within KPI 1 |
Effective Stakeholder Engagement |
2 |
KPI 2 |
Combined SPI 11-15 performance within KPI 2 |
Promote Economic Growth |
3 |
KPI 3 |
Combined SPI 16-17 performance within KPI 3 |
Promote Economic Growth |
4 |
Supply chain strategy |
Delivery of supply chain strategy |
Carbon Neutrality |
5 |
Carbon Reduction Plan |
Delivery of annual Carbon Reduction Plan |
Quality Assurance |
6 |
Business Improvement |
Contractors' performance against contractor's quality plan |